Our cement based precast constituted stone CBOARD Mare Facade Panel products could rapidly be installed by the help of hidden rail fixing system unless there is a special architectural restriction or a Client request. There are two options for horizontal joints where
Installation steps are as follows:
1- Galvanized L brackets are fixed to the wall using suitable wall plugs.
2- Galvanized T or box profiles are vertically fixed to the L brackets.
3- If specified / shown on the Project, chosen heat insulation product is installed between the vertical profiles.
The following steps aside from what is given above differ whether 4mm or 9-10mm horizontal joints are preferred on the facade.
Where 9-10mm horizontal joints are preferred (a):
4a- Hidden horizontal rail profiles are fixed to the vertical profiles considering the panel and joint dimensions.
5a- CBOARD Mare technological stone facade panel is inserted into the upper rail profiles' groove with a sloped movement, then left onto the bottom rail profiles and the installation is completed.
Where 4mm horizontal joints are preferred (b):
4b- Only the bottom rail profiles of the facade are fixed to the vertical profiles.
5b- CBOARD Mare technological stone facade panel is placed to the upper groove of the horizontal profile.
6b- Upper rail profiles are inserted into the upper groove with a space of expansion and fixed to the vertical profiles. Following the same method, the installation is completed from bottom to top of the facade.