Our cement based precast constituted stone CBOARD Mare Facade Panel products could rapidly be installed by the help of hidden rail fixing system unless there is a special architectural restriction or a Client request. There are two options for horizontal joints where


Installation steps are as follows:

1- Galvanized L brackets are fixed to the wall using suitable wall plugs.

2- Galvanized T or box profiles are vertically fixed to the L brackets.

3- If specified / shown on the Project, chosen heat insulation product is installed between the vertical profiles.


The following steps aside from what is given above differ whether 4mm or 9-10mm horizontal joints are preferred on the facade.


Where 9-10mm horizontal joints are preferred (a):

4a- Hidden horizontal rail profiles are fixed to the vertical profiles considering the panel and joint dimensions.

5a- CBOARD Mare technological stone facade panel is inserted into the upper rail profiles' groove with a sloped movement, then left onto the bottom rail profiles and the installation is completed.


Where 4mm horizontal joints are preferred (b):

4b- Only the bottom rail profiles of the facade are fixed to the vertical profiles.

5b- CBOARD Mare technological stone facade panel is placed to the upper groove of the horizontal profile.

6b- Upper rail profiles are inserted into the upper groove with a space of expansion and fixed to the vertical profiles. Following the same method, the installation is completed from bottom to top of the facade.

 
 
 